Governor reports 42% reduction in construction permit processing time
Jenniffer González Colón announced faster timelines for building permits and environmental reviews while environmental groups and planners demand public release of proposed permit reform bill and new hearings.

The short version
- San Juan Daily Star reported average time for Consolidated Construction Permit fell from 107 days in 2024 to 62 days in 2026
- Metro Puerto Rico reported Single Permits adjudication time dropped from 91 to 12 days and environmental recommendations from 167 to 70 days
- Governor González Colón told builders at Condado Vanderbilt hotel that reductions bring investment certainty according to both outlets
- More than 60 organizations asked Senate President Thomas Rivera Schatz and House Speaker Carlos “Johnny” Méndez Núñez to release draft bill and hold new public hearings
Faster permit times announced
Governor Jenniffer González Colón announced on Wednesday, Oct. 7 that the average time to process a Consolidated Construction Permit in Puerto Rico has been reduced from 107 days in 2024 to 62 days in 2026. The San Juan Daily Star reported this represents a 42.1 percent decrease. The governor spoke at the annual convention of the Puerto Rico Builders Association held at the Condado Vanderbilt hotel in San Juan.
The same data show the average time for Single Permit adjudication fell from 91 to 12 days while environmental recommendation processing dropped from 167 to 70 days. Metro Puerto Rico reported the governor linked the improvements to changes her administration has made to the permitting system.
What the sources posted
Posts and statements below are the sources' own words, quoted as published. They are not independently verified.
Los proyectos de ley, en variada forma, implementarían profundos cambios de gran significado y consecuencias negativas en la legislación hoy vigente relacionada con la planificación y el bienestar público y vecinal
Our translation: The bills would in various ways implement deep changes of great significance and negative consequences for current legislation related to planning and public and neighborhood welfare
The source's own statement, as quoted by San Juan Daily Star. Not verified by PuertoRico.com.
Solicitamos que se haga público lo antes posible el borrador del sustitutivo y que se celebren vistas públicas adecuadas
Our translation: We request that the draft of the substitute be made public as soon as possible and that adequate public hearings be held
The source's own statement, as quoted by Metro Puerto Rico. Not verified by PuertoRico.com.
New planning code under debate
González Colón said the proposed new Planning and Permits Code now before the Legislative Assembly should clarify jurisdictions, standardize criteria, create accountability mechanisms and balance economic development with environmental protection. The bill includes an expedited process for projects deemed of high socioeconomic impact, including social-interest housing developments.
The announcement comes as more than 60 organizations, planners and citizens are calling on Senate President Thomas Rivera Schatz and House Speaker Carlos “Johnny” Méndez Núñez to make public the draft substitute version of the permit reform bill. The groups say the document has been shared with certain private-sector associations but not with communities, environmental organizations, planners or other interested parties. They also asked that the official substitute undergo new public hearings.
Environmental and community concerns
Environmental lawyer Pedro Saadé stated in writing that the bills would bring deep changes with negative consequences for current laws on planning, public and neighborhood welfare, coastal access, the environment, natural resources including the karst region, and archaeological sites. He said the draft must be released before the process continues so sectors can evaluate the changes.
Sierra Club Puerto Rico director Hernaliz Vázquez questioned whether prior public hearings on earlier versions of the legislation were sufficient, saying the process has excluded planners, communities, neighbors, environmental groups and experts. Ecologist Ariel Lugo joined the call for the substitute bill to be made public quickly and for adequate public hearings with broad participation from affected sectors.
Reconstruction portfolio update
Separately, Metro Puerto Rico reported the government maintains a reconstruction portfolio of 18,001 projects with estimated investments of $20.375 billion. Completed works rose from 4,262 in December 2024 to 6,127 with $1.723 billion invested. In 2026, $1.5777 billion has been disbursed for recovery work, $254.4 million more than through September 2024.
Of approximately $38.8 billion obligated by the Federal Emergency Management Agency, the Central Office for Recovery, Reconstruction and Resilience has disbursed about $13.3 billion. The Department of Housing has obligated more than $16 billion, or about 75 percent of assigned funds, and disbursed over $6.3 billion. Housing identified 884 priority projects valued at $1.6 billion; 443 have started, representing about $750 million.
Where the sources differ
Both the San Juan Daily Star and Metro Puerto Rico agree on the exact permit processing times, the 42.1 percent reduction figure, the governor’s quotes, the list of reductions for Single Permits and environmental recommendations, and the details of the environmental groups’ demands. The San Juan Daily Star adds the governor’s full name as Jenniffer Aydin González Colón while Metro uses Jenniffer González Colón. Metro Puerto Rico includes an extensive additional section on reconstruction project counts, disbursements and specific housing developments that the San Juan Daily Star does not mention.
What the reports do not say
The reports do not state when the Legislative Assembly will take up the proposed Planning and Permits Code, whether the draft will be released before further action, or if new public hearings will be scheduled. They give no timeline for when the current reductions in processing times might be codified or expanded, nor do they specify how many projects have used the faster procedures or the total investment value tied directly to the improved timelines.
Sources
Every link below was opened and checked when this story was published. Official means a government body, agency or the organization itself; Reporting means a news outlet.
- Official Gobernadora informa reducción de 42 por ciento en tiempo para tramitar permisos de construcción
- Reporting Gobernadora informa reducción de 42 por ciento en tiempo para tramitar permisos de construcción
- Reporting Gobernadora informa reducción en el tiempo para tramitar permisos de construcción
How we checked this
The San Juan Daily Star and Metro Puerto Rico both covered the governor’s announcement on permit reductions and the environmental groups’ calls for transparency on the reform bill. Reconstruction statistics and specific housing project names appear only in the Metro Puerto Rico account.
Compiled by the PuertoRico.com News Desk from the reports and statements listed above, and checked against them before publishing. It does not include original interviews. Spot an error? Email support@puertorico.com with a link to this story.