The short version
- Telemundo Puerto Rico reported the NEPR issued the order on Tuesday requiring LUMA to submit technical studies within eight weeks on connecting 800 MW of temporary generation
- All four outlets agree on a generation deficit of 700-850 MW identified by LUMA with peak demand reaching about 3,234 MW in August 2026
- LUMA must study sites including Aguirre, San Juan, Palo Seco, Costa Sur and Sabana Llana plus alternatives such as Cambalache, Yabucoa and Mayagüez according to the resolution
- NotiCel and Telemundo Puerto Rico reported that LUMA returned $400,000 authorized for the studies and reported $270,889.23 in internal costs without delivering the work
Updates
Update, Oct 14, 9:42 AM AST
Telemundo Puerto Rico adds that NEPR requires at least one viable combination delivering 800 MW net new capacity and clarifies the July 2025 resolution did not order new procurement.
Telemundo Puerto Rico reported on Wednesday that the NEPR order additionally requires LUMA to present at least one technically viable combination of installations that allows the incorporation of 800 MW of net additional capacity, meaning capacity that simply replaces existing generation without increasing total system availability cannot be counted. Telemundo Puerto Rico reported
The new report also states that the regulator clarified its July 2025 resolution did not order the start of a new procurement process for temporary generation, contrary to the interpretation attributed to the Independent Office of Acquisitions and the Public-Private Partnerships Authority; the decision to issue another request for proposals was made solely by the acquisitions office.
Telemundo Puerto Rico's account is otherwise consistent with prior reporting on the eight-week deadline, the 700-850 MW deficit, peak demand of 3,234 MW in August 2026, the listed study sites, the six-month operational requirement, returned funds of $400,000, internal costs of $270,889.23 and potential daily fines.
Update, Oct 14, 6:04 AM AST
NotiCel adds details on LUMA returning $400k in authorized funds, incurring $270k internal costs without delivering studies, and clarifies the July 2025 resolution did not order new procurement.
NotiCel reported on Wednesday that the Puerto Rico Energy Bureau issued the order on Tuesday, Oct. 13. NotiCel reported The new account states LUMA had been authorized $400,000 to perform the studies but returned those funds to customers while reporting $270,889.23 in internal costs without completing the required system impact or facility studies.
The regulator clarified that its July 2025 resolution did not order a new procurement process for temporary generation, contrary to interpretations by the Independent Procurement Office and the Public-Private Partnerships Authority. NotiCel reported that the decision to issue a new request for proposals was made solely by the procurement office.
NotiCel's coverage otherwise aligns with the prior reports on the eight-week deadline, the 700-850 MW deficit, peak demand of 3,234 MW in August 2026, required study sites, six-month online timeline and potential daily administrative fines for noncompliance.
Order Issued
The Puerto Rico Energy Bureau (NEPR) has ordered LUMA Energy to complete and present technical studies within a maximum of eight weeks to identify where and how 800 megawatts of temporary generation can be connected to the electric system. Metro Puerto Rico reported. The order requires LUMA to specify how much energy the grid can safely receive at each connection point, what work would be needed and the associated costs.
The determination responds to a generation deficit of between 700 and 850 MW that LUMA identified in an updated evaluation. Both Metro Puerto Rico and El Vocero reported that maximum demand reached approximately 3,234 MW in August 2026. The resolution states that the persistence of the deficit identified by LUMA requires determining without further delay the network's capacity to receive the 800 MW required by the Priority Plan.
Also on PuertoRico.com: Puerto Rico power and water outages
What the sources posted
Posts and statements below are the sources' own words, quoted as published. They are not independently verified.
La persistencia del déficit identificado por LUMA exige determinar, sin más dilación, la capacidad de la red para recibir los 800 MW que requiere el Plan Prioritario
Our translation: The persistence of the deficit identified by LUMA requires determining, without further delay, the capacity of the network to receive the 800 MW required by the Priority Plan
The source's own statement, as quoted by Metro Puerto Rico. Not verified by PuertoRico.com.
Scope of Studies
LUMA must carry out the studies independently of the processes to contract temporary generation. The eight-week term corresponds to the delivery of supported technical results and not merely to the presentation of a plan to conduct studies at a later date, according to the order reported by both outlets. LUMA must evaluate potential connection points in Aguirre, San Juan, Palo Seco, Costa Sur and Sabana Llana. It must also identify other alternatives in Puerto Rico and consider at a minimum the facilities at Cambalache, Yabucoa and Mayagüez.
For each point the report must distinguish how much generation can be incorporated with existing infrastructure and minor works and how much would require additional improvements. The studies must also identify the equipment, costs, supply times and parties responsible for the work. The evaluation must reflect the real increase in available capacity and the schedule must allow temporary generation to supply energy to the system no later than six months from the signing of the corresponding contract.
Requirements and Penalties
LUMA must coordinate with the Puerto Rico Electric Power Authority and Genera to validate facility information, but that coordination does not release it from meeting the deadline. If obstacles exist to meeting the six-month timeline, LUMA must explain the technical basis and identify alternatives, El Vocero reported.
The NEPR warned that noncompliance could result in administrative fines for each day of delay and other sanctions authorized by law. The order notes that LUMA had not previously performed the contemplated system impact and facility studies and that its prior analysis was limited to a preliminary evaluation from March 2025.
Where the sources differ
Metro Puerto Rico, El Vocero, NotiCel and Telemundo Puerto Rico agree on all core facts including the eight-week deadline, the 700-850 MW deficit, peak demand of 3,234 MW in August 2026, the listed study sites, the six-month online requirement, potential daily fines for noncompliance, the requirement for net new capacity and the clarification on the July 2025 resolution. NotiCel and Telemundo add that the order was issued on Tuesday, Oct. 13, that LUMA returned $400,000 in authorized study funds while incurring $270,889.23 in internal costs without results, and that the July 2025 resolution did not order new procurement. The four reports are otherwise consistent with no contradictions on numbers, dates or requirements.
What the reports do not say
The reports do not state when the order was formally notified to LUMA, the exact start date of the eight-week clock, whether any temporary generation procurement has already begun, the current status of the Priority Plan, what specific penalties beyond daily fines could be imposed or the expected cost range for any required grid upgrades. They also do not indicate if LUMA has identified any technically viable combination of sites that would deliver the full 800 MW of net new capacity.
Sources
Every link below was opened and checked when this story was published and last updated. Official means a government body, agency or the organization itself; Reporting means a news outlet.
- Official Negociado de Energía ordena a LUMA identificar dónde conectar 800 megavatios de generación temporera
- Reporting Negociado de Energía ordena a LUMA identificar dónde conectar 800 megavatios de generación temporera
- Reporting Dan ocho semanas a LUMA para definir cómo conectar 800 megavatios de generación temporera
- Reporting NE da ocho semanas a LUMA para identificar dónde conectar 800 MW de generación temporera
- Reporting LUMA tendrá ocho semanas para ubicar conexión de 800 MW de generación temporera
How we checked this
Metro Puerto Rico, El Vocero, NotiCel and Telemundo Puerto Rico reported the details of the NEPR resolution. The requirement for at least one viable net-new 800 MW combination and the clarification on the July 2025 resolution rest on the Telemundo Puerto Rico account while the financial details on returned funds and internal costs rest on NotiCel and Telemundo Puerto Rico.
Compiled by the PuertoRico.com News Desk from the reports and statements listed above, and checked against them before publishing. It does not include original interviews. Spot an error? Email support@puertorico.com with a link to this story.
Nils Huenerfuerst / Wikimedia Commons · CC BY 4.0PuertoRico.com is free, and readers like you keep it that way.
The PuertoRico.com newsroom checks every story against its sources and publishes it free. If this one helped, a contribution of any size keeps the next one free too.
Secure checkout by Stripe: card, Apple Pay, Google Pay or Link.
One payment, nothing to sign up for.
Contributions go to Puerto Rico.com, LLC. They are not charitable donations and are not tax-deductible. Payments are processed by Stripe.
Thank you for keeping PuertoRico.com free.
Your contribution went through. It helps pay for the next story.
Contributions go to Puerto Rico.com, LLC. They are not charitable donations and are not tax-deductible. Payments are processed by Stripe.